Background

The Hutchinson Correctional Facility (HCF) is the second-largest facility in Kansas housing male adults, with a capacity of 1,810 residents at four custody levels: maximum, special management, medium, and minimum.

The facility employs 507 full-time state employees, more than 85 contract employees, and has an annual operating budget of $47.3 million.

The majority of the structures composing HCF were built prior to 1912, which makes HCF the oldest correctional facility maintained by the Kansas Department of Corrections (KDOC). As an older facility, HCF no longer complies with safety requirements, such as minimum cell sizes and fire safety sprinkler systems, set by the Americans with Disabilities Act (ADA) and the American Correctional Association.

In 2021, KDOC contracted with Carter Global Lee (CGL), a criminal justice consulting firm, to conduct an equipment and facility assessment of the site. CGL’s report concluded that it would be more cost effective to build a new facility than to renovate the existing facility.

The CGL report identified $80.2 million in capital needs over a 10-year period to address deficiencies in mechanical, electrical, and plumbing systems; roofs; foundations; exterior enclosures; fire safety systems; and interior constructions. However, not included in this estimate is the cost to bring the facility up to ADA standards, to retrofit air conditioning into the housing units, and to increase cell sizes, as well as other possible issues not addressed due to the inspection being purely visual.

Courtesy of Kansas Department of Corrections

Plans

KDOC plans to construct a new facility incorporating modern correctional design and systems on adjacent land already owned by the agency.

Plans for the facility include:

  • 20,000 square feet of program space;
  • 105,000 square feet of private industry space;
  • Consolidating the medium- and maximum-security housing units for a total of 1,792 beds; and
  • A separate minimum security housing unit outside the secure perimeter with 400 beds.

The agency intends to seek an appropriation of approximately $453 million from the State General Fund for fiscal year 2026 to fund construction of the new facility.

A representative of KDOC presented the agency’s plan for the new facility to the J. Russell (Russ) Jennings Joint Committee on Corrections and Juvenile Justice Oversight on November 19, 2024. The Committee recommended the Joint Committee on State Building Construction move forward with consideration on replacement of HCF.
KDOC plans to present the agency’s Five-year Capital Improvements Plan to the Joint Committee on State Building Construction at the Committee’s next meeting, scheduled for December 2024. During this presentation, the agency intends to discuss the deficiencies of the current HCF and its plans for a new facility.

For more information, contact:

Nicole Hrenchir
Fiscal Analyst

Natalie Nelson
Principal Research Analyst

Kansas Legislative Research Department
Kansas State Capitol Building
300 W. 10th, Suite 68-West
Topeka KS 66612-1504
kslegres@klrd.ks.gov
(785) 296-3181